| NO. | PROJECT & LOCATION | DURATION | SCOPE OF WORK | OWNER / CLIENT | INSPECTION / |
| SUPERVISION | |||||
| 1 | ELECTRICAL & | 6-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | SAUDI ARAMCO | |
| INSTRUMENTATION | 2005-2006 | ELECTRICAL, INSTRUMENTATION AND SCADA | Saudi Aramco | INSPECTIONS | |
| AND SCADA | SYSTEMS FOR RTUS ON WELL HEADS | DEPARTMENT | |||
| FOR HARADH GOSP-3 | 1. ELECTRICAL | ||||
| STARTUP WELLS | a. Main Power supply | ||||
| HARADH, SAUDI ARABIA | b. L.V Transformers | ||||
| c. Power Panel Boards | |||||
| d. Starters, Pushbutton stations. | |||||
| e. Disconnect switches | |||||
| f. Switch Racks, Cable trays, conduits and fittings | |||||
| g. LV cables | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. DCS Marshalling Cabinets | |||||
| b. SCADA control cabinets | |||||
| c. Digital & Analog process instruments | |||||
| d. Digital & Analog Field Junction Boxes. | |||||
| e. Calibration of field instruments | |||||
| f. Switch Racks, Cable trays, RGS/PVC coated | |||||
| conduits and fittings | |||||
| g. Control, instrumentation & comm: cables | |||||
| h. Termination & loop checks | |||||
| i. Precommissioning & startup. | |||||
| 2 | ELECTRICAL & | 6-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | SAUDI ARAMCO | |
| COMMUNICATION WORKS | 2005-2006 | ELECTRICAL, ELECTRICAL AND COMM: | Saudi Aramco | INSPECTIONS | |
| FOR SCADA SYSTEM | SYSTEMS | DEPARTMENT | |||
| AT UTHMANIYAH | 1. ELECTRICAL | ||||
| GAS PLANT | a. Main Power supply | ||||
| UTHMANIYAH, SAUDI ARABIA | b. L.V Transformers | ||||
| c. Power Panel Boards | |||||
| d. Disconnect switches | |||||
| e. RGS conduits and fittings | |||||
| f. LV cables | |||||
| 2. COMMUNICATION WORKS | |||||
| a. DCS Marshalling Cabinets | |||||
| b. SCADA control consoles | |||||
| c. Cable trays, RGS conduits and fittings | |||||
| d. Data cables | |||||
| e. Data outlets | |||||
| f. Termination & loop checks | |||||
| g. Precommissioning & startup. | |||||
| 3 | ELECTRICAL & | 8-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| INSTRUMENTATION | 2006-2007 | ELECTRICAL & INSTRUMENTATION WORKS | Saudi German | Saudi Engineering | |
| AT SAUDI GERMAN PLANT | 1. ELECTRICAL | Industries-Dammam | Dammam | ||
| FOR NON WOVEN FIBRE | a. MV Package substations | ||||
| DAMMAM INDUSTRIAL | b. Ring Main Units | ||||
| AREA-II | c. Distribution Transformers | ||||
| d. LV switchgears | |||||
| e. Power Bus Ducts | |||||
| f. Motor control centres | |||||
| g. Panel Boards, starters, Pushbutton stations. | |||||
| h. Disconnect switches | |||||
| i. Lighting system | |||||
| k. Pipe Racks, Cable trays, conduits and fittings | |||||
| l. HV/LV cables | |||||
| m Control cables | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. DCS Marshalling Cabinets | |||||
| b. DCS control consoles | |||||
| c. Digital & Analog process instruments | |||||
| d. Digital & Analog Field Junction Boxes. | |||||
| e. Calibration of field instruments | |||||
| f. Pipe Racks, Cable trays, conduits and fittings | |||||
| g. Control, digital & analog cables | |||||
| h. Termination & loop checks | |||||
| h. Precommissioning & Plant startup. | |||||
| 4 | ELECTRICAL & | 12-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| INSTRUMENTATION | 2006-2007 | ELECTRICAL & INSTRUMENTATION WORKS | JANA | HASSAD | |
| AT JANA PLANT | 1. ELECTRICAL | ||||
| JUBAIL INDUSTRIAL | a. MV switchgear Lineup | ||||
| AREA | b. Power Transformers | ||||
| c. Distribution Transformers | |||||
| d. Rectifier transformers | |||||
| e. Power Bus Ducts | |||||
| f. LV switchgears | |||||
| g. Motor control centres | |||||
| h. Power factor correction equipment | |||||
| i. Panel Boards, starters, Pushbutton stations. | |||||
| k.Disconnect switches | |||||
| l. Pipe Racks, Cable trays, conduits and fittings | |||||
| m HV/LV cables | |||||
| n. Control cables | |||||
| 0. Plant Lighting & Power Distribution network | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. DCS Marshalling Cabinets | |||||
| b. DCS control consoles | |||||
| c. Digital & Analog process instruments | |||||
| d. Digital & Analog Field Junction Boxes. | |||||
| e. Calibration of field instruments | |||||
| f. Pipe Racks, Cable trays, conduits and fittings | |||||
| g. Control, digital & analog cables | |||||
| h. Termination & loop checks | |||||
| h. Precommissioning & Plant startup. | |||||
| 3. COMMUNICATION WORKS | |||||
| a. Cable trays, RGS conduits and fittings | |||||
| b. SCADA control consoles | |||||
| c. Data cables | |||||
| d. Data outlets | |||||
| e. Termination & loop checks | |||||
| f. Precommissioning & startup. | |||||
| 5 | ELECTRICAL WORKS | 08-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| AT BISCHOF + KLIEN | 2006-2007 | ELECTRICAL & INSTRUMENTATION WORKS | BISHOF + KLIEN | B+K | |
| MIDDLE EAST CO. | 1. ELECTRICAL | MIDDLE EAST CO. | |||
| DAMMAM INDUSTRIAL | a. Ring Main Units | ||||
| AREA – II | b. Distribution Transformers | ||||
| c. LV switchgears | |||||
| d. Power Bus Ducts | |||||
| e. Motor control centres | |||||
| f. Panel Boards, starters, Pushbutton stations. | |||||
| g. Disconnect switches | |||||
| h. Lighting system | |||||
| i. Cable trays, conduits and fittings | |||||
| j. HV/LV cables | |||||
| k Control cables | |||||
| l. Fire Alarm System | |||||
| 6 | TIMELINE SADAF | 1.5-MONTH | DCS CONTROL, HMI & ELECTROMECHANICAL | SADAF | ABB |
| EDC T/A 2007 | Jan-Feb 2007 | WORKS DURING SHUTDOWN PERIOD | SWITZERLAND | ||
| SAUDI PETROCHEMICAL | 1. CONTROL ROOM | ||||
| CO. (SADAF) JUBAIL | a. Removal of existing HMI. | ||||
| b. Installation of New HMI | |||||
| c. Disconnect & removal of existing control cables | |||||
| d. Installation of New Control cables from | |||||
| Marshalling rack to New HMI | |||||
| f. Modification of existing DCs Panel to increase | |||||
| Capacity | |||||
| 2. RECTIFIER TRANSFORMERS – 6 EA | |||||
| a Dismental & remove existing power & control | |||||
| wiring for rectifier transformers including control | |||||
| panel. | |||||
| b. Installation of New control panel for rectifier | |||||
| transformers. | |||||
| c. Modification work at Pan alarm panel | |||||
| d. Installation of cotnrol & communication wiring | |||||
| from rectifier transformer and marshalling racks. | |||||
| e. Preloop checks & final loop checks. | |||||
| f. Replacement of RTD’s at rectifier transformer | |||||
| g. Replacemnt of existing switches & transmitter. | |||||
| 3. MECHANICAL WORKS | |||||
| a. Cleaning of rectifier transformer bushing with | |||||
| Demi water. | |||||
| b. Replacement of gaskits. | |||||
| c. Replacement of mehcanical piping at various | |||||
| Locations. | |||||
| d. Re-circulation & Dehumidification of | |||||
| transformer oil. | |||||
| 7 | FOUNDATION HEATING | 4-MONTHS | LSTK INSTALLATION OF THE FOLLOWING ELECTRICAL | SHARQ/SABIC | FOSTER WHEELER |
| SYSTEM FOR TANKS | 2007-2008 | AND HEATING SYSTEM WORK. | FOSTER WHEELER | ACBI LTD | |
| AT SHARQ-III EXPENSION | 1. ELECTRICAL | ||||
| PROJ.# 1-14-2460/2519 | a. Marshaling Panel for Heating system | ||||
| JUBAIL IND. CITY | b. Marshaling Panel for Cool down system | ||||
| c. Control Panel for Heating / Cool Down system | |||||
| d. Power JB’s for Heating elements/RTD’s | |||||
| e. Power / Heating Cable | |||||
| f. RTD’s for Heating / Cool Down system | |||||
| g. Cable trys, Conduit & Fitting | |||||
| h. Grounding system | |||||
| 8 | HVAC / FIRE FIGHTING | 06-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| WORKS AT IBN-ZAHR | 2007-2008 | HVAC & FIRE FIGHTING SYSTEM | IBN-ZAHR | DAELIM/KCC | |
| EXPENSION PROJECT | 1. HVAC | DAELIM S.A. | JUBAIL | ||
| JUBAIL INDUSTRIAL CITY | a. 50-Ton Package A/C units | ||||
| b. 5-Ton Split A/C units | |||||
| c. Power and Control Cables | |||||
| d. Control Panel | |||||
| e. Duct Work, Insulation & Cladding | |||||
| f. Refrigerant Piping, Instulation & Cladding | |||||
| g. Cable Tray Conduit & Fittings | |||||
| h. Testing & Commissioning | |||||
| 2. FIRE FIGHTING | |||||
| a. Above Ground Fire Water Piping System | |||||
| b. FM-200 System | |||||
| c. Fire Hydrant & Assocciate Equipment | |||||
| d. Tesing & Commissioning | |||||
| 9 | CASE WORK & GAS | 3-MONTHS | LSTK INSTALLATION OF THE FOLLOWING SYSTEM | IBN-ZAHR | DAELIM/KCC |
| TUBING NET WORK AT | 2008 | DAELIM S.A. | JUBAIL | ||
| LAB BUILDING IBN-ZAHR | 1. GAS PIPING + BUNKER | ||||
| JUBAIL IND. CITY | a. Installation of SS-Tubing network for the | ||||
| following gases & Utilities: | |||||
| * HE ( HELIUM ) | |||||
| * N2 ( NITROGEN ) | |||||
| * O2 ( OXYGEN ) | |||||
| * ARGON | |||||
| * IA ( INST. AIR ) | |||||
| * PW ( PORTABLE WATER ) | |||||
| * NO ( NITREX OXIDE ) | |||||
| * 3-Stage Manifolds | |||||
| * Air Seperator Filter System | |||||
| * Testing & Commissioning | |||||
| 2. CASE WORK | |||||
| a. Installation of LAB Accessories for the following | |||||
| * Fume Hood | |||||
| * Work Benches | |||||
| * Plumbing for Case Work | |||||
| * Electrical for Case work | |||||
| * Power Out let | |||||
| * Data Out let | |||||
| * Wiring & Termination | |||||
| 10 | CASE WORK & GAS | 4-MONTHS | LSTK INSTALLATION OF THE FOLLOWING SYSTEM | SIPCHEM | FLOUR S.A |
| UTILITIES NETWORK AT | 2008 | 1. GAS PIPING + BUNKER | JUBAIL | ||
| SAUDI INTERNATIONAL | a. Installation of SS-Tubing network for the | ||||
| PETRO CHEMICAL CO. | following gases & Utilities: | ||||
| SIPCHEM – JUBAIL | * HE ( HELIUM ) | ||||
| CONTRACT#JAC-C-173-B | * N2 ( NITROGEN ) | ||||
| * O2 ( OXYGEN ) | |||||
| * ARGON | |||||
| * IA ( INST. AIR ) | |||||
| * PW ( PORTABLE WATER ) | |||||
| * NO ( NITREX OXIDE ) | |||||
| * 3-Stage Manifolds | |||||
| * Air Seperator Filter System | |||||
| * Testing & Commissioning | |||||
| 2. CASE WORK | |||||
| a. Installation of LAB Accessories for the following | |||||
| * Fume Hood | |||||
| * Work Benches | |||||
| * Plumbing for Case Work | |||||
| * Electrical for Case work | |||||
| * Power Out let | |||||
| * Data Out let | |||||
| * Wiring & Termination | |||||
| 11 | ELECTRICAL & | 06-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| INSTRUMENTATION AT | 2008 | ELECTRICAL & INSTRUMENTATION WORKS | SAUDI ARAMCO | AL-KHODARI | |
| TURAIF BULK PLANT-X20 | 1. ELECTRICAL | & SONS CO. | |||
| SAUDI ARAMCO | a. Power Bus Ducts | SAPMT | |||
| JO/EWO# 10-00084/0001 | b. LV switchgears | ||||
| SA-CONT#6600018226 | c. Motor control centres | ||||
| SA-CONT#6600018227 | d. Panel Boards, starters, Pushbutton stations. | ||||
| e.Disconnect switches | |||||
| f. Cable trays, conduits and fittings | |||||
| g LV cables | |||||
| h. Control cables | |||||
| i. Plant Lighting & Power Distribution network | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. Digital & Analog process instruments | |||||
| b. Digital & Analog Field Junction Boxes. | |||||
| c. Calibration of field instruments | |||||
| d. Cable trays, conduits and fittings | |||||
| e. Control, digital & analog cables | |||||
| f. Termination & loop checks | |||||
| g. Precommissioning & Plant startup. | |||||
| 12 | ELECTRICAL & | 06-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | SAUDI ARAMCO | AL-KHODARI |
| INSTRUMENTATION AT | 2008 | ELECTRICAL & INSTRUMENTATION WORKS | & SONS CO. | ||
| JOUF BULK PLANT-X19 | 1. ELECTRICAL | SAPMT | |||
| SAUDI ARAMCO | a. Power Bus Ducts | ||||
| JO/EWO# 10-00084/0001 | b. LV switchgears | ||||
| SA-CONT#6600018226 | c. Motor control centres | ||||
| SA-CONT#6600018227 | d. Panel Boards, starters, Pushbutton stations. | ||||
| e.Disconnect switches | |||||
| f. Cable trays, conduits and fittings | |||||
| g LV cables | |||||
| h. Control cables | |||||
| i. Plant Lighting & Power Distribution network | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. Digital & Analog process instruments | |||||
| b. Digital & Analog Field Junction Boxes. | |||||
| c. Calibration of field instruments | |||||
| d. Cable trays, conduits and fittings | |||||
| e. Control, digital & analog cables | |||||
| f. Termination & loop checks | |||||
| g. Precommissioning & Plant startup. | |||||
| 13 | HVAC / FIRE FIGHTING | 04-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| WORKS AT LAB BUILDING | 2008 | HVAC & FIRE FIGHTING SYSTEM | AR-RAZI | MHI / KCC | |
| AR-RAZI METHONAL | 1. HVAC | MHI | JUBAIL | ||
| PROJECT PLANT-V | a. 50-Ton Package A/C units | ||||
| JUBAIL INDUSTRIAL CITY | b. 5-Ton Split A/C units | ||||
| Contract# 533570 | c. Power and Control Cables | ||||
| d. Control Panel | |||||
| e. Duct Work, Insulation & Cladding | |||||
| f. Refrigerant Piping, Instulation & Cladding | |||||
| g. Cable Tray Conduit & Fittings | |||||
| h. Testing & Commissioning | |||||
| 2. FIRE FIGHTING | |||||
| a. Above Ground Fire Water Piping System | |||||
| b. FM-200 System | |||||
| c. Fire Hydrant & Assocciate Equipment | |||||
| d. Tesing & Commissioning | |||||
| 14 | HVAC WORKS AT | 3-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | SASREF | SASREF / |
| AT SASREF JUBAIL | 2008 | HVAC SYSTEM | CARRIER | ||
| a- 50 Ton Package A/C Units | |||||
| b. Power and Control Cables | |||||
| c. Control Panel | |||||
| d. Duct Work, Insulation & Cladding | |||||
| e. Refrigerant Piping, Instulation & Cladding | |||||
| f. Cable Tray Conduit & Fittings | |||||
| g. Testing & Commissioning | |||||
| 15 | ONLINE ANALYZER FOR | 2-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | SASREF | SASREF / |
| OIL & BENZENE | 2008 | ABDULALH FOUAD | |||
| AT SASREF JUBAIL | a- Analyzer | ||||
| b- Cable Tray Conduit & Fittings | |||||
| c- Sampling Tube Laying & termination. | |||||
| d. Power and Control Cables | |||||
| e- Hookup with DCS in Control Room. | |||||
| 16 | ELECTRICAL & | 8-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| INSTRUMENTATION | 2009 | ELECTRICAL & INSTRUMENTATION WORKS | PROCTER & GAMBLE | MIC / | |
| AT CORNFLAKE PLANT | 1. ELECTRICAL | CHEMOPRAG, | |||
| 2ND INDUSTRIAL CITY | a. MV switchgear Lineup | CHEZK REPUBLIC | |||
| DAMMAM | b. Power Transformers | ||||
| c. Distribution Transformers | |||||
| d. Rectifier transformers | |||||
| e. Power Bus Ducts | |||||
| f. LV switchgears | |||||
| g. Motor control centres | |||||
| h. Power factor correction equipment | |||||
| i. Panel Boards, starters, Pushbutton stations. | |||||
| k.Disconnect switches | |||||
| l. Pipe Racks, Cable trays, conduits and fittings | |||||
| m HV/LV cables | |||||
| n. Control cables | |||||
| 0. Plant Lighting & Power Distribution network | |||||
| 2. INSTRUMENTATION WORKS | |||||
| a. DCS Marshalling Cabinets | |||||
| b. DCS control consoles | |||||
| c. Digital & Analog process instruments | |||||
| d. Digital & Analog Field Junction Boxes. | |||||
| e. Calibration of field instruments | |||||
| f. Pipe Racks, Cable trays, conduits and fittings | |||||
| g. Control, digital & analog cables | |||||
| h. Termination & loop checks | |||||
| h. Precommissioning & Plant startup. | |||||
| 17 | HVAC / FIRE FIGHTING / | 1-YEAR | LSTK INSTALLATION OF THE FOLLOWING | ||
| ELECTRICAL / BMS WORKS | 2009-2010 | HVAC & FIRE FIGHTING SYSTEM | AAC ETHYLENE | AAC / | |
| AT AAC ETHYLENE AMINES | 1. HVAC | AMINE | HANWHA SAUDI | ||
| PLANT | a. Chiller | CONTRACTING CO. | |||
| JUBAIL INDUSTRIAL CITY | b. Package units | LTD. | |||
| Contract# HSCC-AAC-027 | c. Splilt units | ||||
| d. AHUs | |||||
| e. HRUs, ARUs, EFU | |||||
| f. Power & Control Cables | |||||
| g. Control Panel | |||||
| h. Duct work, Insulation & Cladding | |||||
| i. Refrigerant Piping, Insulation & Cladding | |||||
| j. Cable Tray, Conduit & Fittings | |||||
| k. Testing & Commissioning | |||||
| 2. FIRE FIGHTING | |||||
| a. Above Ground Fire Water Piping System | |||||
| b. FM-200 System | |||||
| c. Fire Hydrant & Associate Equipment | |||||
| d. Testing & Commissioning | |||||
| 3. PLUMBING | |||||
| a. Hot & Cold water system | |||||
| b. Drain & Sewer water system | |||||
| c. Chemical Drainage system | |||||
| d. Plumbing Fixtures & Fittings | |||||
| e. Eye wash & Safety Shower | |||||
| f. Copper piping Networks | |||||
| 18 | ELECTRICAL WORKS FOR | 4-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| NEW PSG BUILDING | 2009-2010 | ELECTRICAL & DATA NETWORKING | PROCTER & GAMBLE | MIC | |
| AT PROCTOR & GAMBLE | 1. ELECTRICAL | ||||
| MODERN INDUS. CO. | a. LV switchgear Lineup | ||||
| DAMMAM | b. Distribution Transformers | ||||
| c. Motor control centres | |||||
| d. Panel Boards, starters, Pushbutton stations. | |||||
| e. Disconnect switches | |||||
| f. Pipe Racks, Cable trays, conduits and fittings | |||||
| g. LV cables | |||||
| h. Control cables | |||||
| i. Plant Lighting & Power Distribution network | |||||
| 2. TELEPHONE & DATA NETWORKS | |||||
| a. Data Panels | |||||
| b. Telephone & Data Outlets | |||||
| C. Patch Cords & Patch Panels | |||||
| d. Cable trays, conduits and fittings | |||||
| e. Termination & loop checks | |||||
| f. Precommissioning & startup. | |||||
| 19 | MEDUIM VOLTAGE | 3-MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| POWER DISTRIBUTION | 2010 | ELECTRICAL WORKS | PROCTER & GAMBLE | MIC | |
| NETWORKS @ | 1. ELECTRICAL | ||||
| P&G / MIC | a. MV Package substations | ||||
| DAMMAM INDUSTRIAL | b. Ring Main Units | ||||
| AREA-II | c. Distribution Transformers | ||||
| d. LV switchgears | |||||
| e. Power Bus Ducts | |||||
| f. Motor control centres | |||||
| g. MV REYCHEM Termination & Hi-pot | |||||
| h. Pipe Racks, Cable trays, conduits and fittings | |||||
| l. HV/LV cables | |||||
| 20 | CASE WORK & GAS | 8-MONTHS | LSTK INSTALLATION OF THE FOLLOWING SYSTEM | ||
| UTILITIES NETWORK AT | 2010 | 1. GAS PIPING + BUNKER | TASNEE | AFM CONSULTING | |
| TASNEE PLASTIC RESEARCH | a. Installation of SS-Tubing network for the | H&H SCIENTIFIC | |||
| CENTER – JUBAIL | following gases & Utilities: | CANADA | |||
| CONTRACT#4500014754 | * HE ( HELIUM ) | ||||
| * N2 ( NITROGEN ) | |||||
| * O2 ( OXYGEN ) | |||||
| * ARGON | |||||
| * IA ( INST. AIR ) | |||||
| * PW ( PORTABLE WATER ) | |||||
| * NO ( NITREX OXIDE ) | |||||
| * 3-Stage Manifolds | |||||
| * Air Seperator Filter System | |||||
| * Testing & Commissioning | |||||
| 2. CASE WORK | |||||
| a. Installation of LAB Accessories for the following | |||||
| * Fume Hood | |||||
| * Work Benches | |||||
| * Plumbing for Case Work | |||||
| * Electrical for Case work | |||||
| * Power Out let | |||||
| * Data Out let | |||||
| * Wiring & Termination | |||||
| 21 | ELECTRO MECHANICAL | 9-MONTHS | LSTK INSTALLATION OF THE FOLLOWING SYSTEM | ||
| WORKS AT | 2010 | TASNEE | AFM CONSULTING | ||
| TASNEE PLASTIC RESEARCH | 1. PROCESS COOLING SYSTEM | ||||
| CENTER – JUBAIL | a. 200 Ton Chiller | ||||
| CONTRACT#4500016585 | b. Heat Exchanger, ch.water pump, pw pumps | ||||
| c. 6″ chiller water line for all process machines | |||||
| d. 3″ chilled water riser to the headers, | |||||
| e. Complete system upto the commissioning. | |||||
| 2. COMPRESSED AIR SYSTEM | |||||
| a. 2″ air line to all process machines | |||||
| b. Compressor and filtration system including | |||||
| tank | |||||
| c. Commissioning of complete system | |||||
| 3. MACHINE ERECTION | |||||
| a. Below film line | |||||
| b. Small injector | |||||
| c. Large below film line | |||||
| d. Large injector machine | |||||
| E. Pipe extruder | |||||
| F. Chiller units | |||||
| g. Testing & Commissioning of all Machine’s | |||||
| 22 | INSTALLATION OF MV/LV | 1-Year | INSTALLATION OF THE FOLLOWING | ||
| CABLE NETWORK | 2010-2011 | MV/LV CABLES INCLUDING TEMINATION & TESTING | SAUDI ARAMCO | EYP / S.ARAMCO | |
| INCLUDING TERMINATION | Latifia Cont. Co. Ltd. | Inspection Depart. | |||
| AND TESTING AT SAUDI | a. 15-KV, Underground cables in duct bank | ||||
| ARAMCO CORPORATE | b. 7.2-Kv Cables in duct bank | ||||
| DATA CENTER – DHAHRAN | c. LV Cable in duct bank, cable tray & Conduits | ||||
| Contract & BI NO. | d. 15-KV, splicing & terminations | ||||
| 6600021541 / 10-00273 | e. Dressing, termination, tagging of MV cables | ||||
| f. Meggering & Hi-pot | |||||
| g. Dressing, termination, tagging of LV cables | |||||
| h. Insulation resistance testing of a power & control cables |
|||||
| 23 | INSTALLATION OF MV/LV | 1-Year | INSTALLATION OF THE FOLLOWING | ||
| POWER SYSTEM EQUIPMENTS | 2011-2012 | ELECTRICAL EQUIPMENTS | SAUDI ARAMCO | EYP / S.ARAMCO | |
| AT SAUDI ARAMCO | a. 13.8 KV, double ended Utility switchgears | Latifia Cont. Co. Ltd. | Inspection Depart. | ||
| CORPORATE DATA CENTER | b. 13.8 KV double ended Paralleling Switchgear | ||||
| DHAHRAN | c. 5 KV double ended Switchgear | ||||
| Contract & BI NO. | d. 13.8KV, Automatic Transfer Switches | ||||
| 6600021541 / 10-00273 | e. 13.8 KV Manual Transfer Switches | ||||
| f. 3.75MVA, Power transformers | |||||
| g. 7.5 MVA power transpformers | |||||
| h. LV Dry Type Transformers | |||||
| i. 480V, double ended LV Switchgears | |||||
| j. 750 KVA UPS | |||||
| k. 40 KVA UPS | |||||
| l. 85 KVA UPS | |||||
| m. Static Transfer Switches | |||||
| n. Motor Control Centers | |||||
| o. Power distribution units (PDUS) | |||||
| p. RPP | |||||
| q. LV, Distribution Panel Boards | |||||
| r. LV Automatic tranfer switches | |||||
| s. DC, Disconnect Switchs | |||||
| t. Batteries, battry banks & Battery Chargers | |||||
| 24 | INSTALLATION OF MV/LV | 1-Year | INSTALLATION OF THE FOLLOWING | ||
| EMERGENCY POWER SYSTEM | 2011-2012 | a. 6-Ea, 2 MVA, 13.8 KV, Diesel engine generators | SAUDI ARAMCO | EYP / S.ARAMCO | |
| AT SAUDI ARAMCO | a. 6-Ea, Diesel fuel tanks | Latifia Cont. Co. Ltd. | Inspection Depart. | ||
| CORPORATE DATA CENTER | b. Fuel polishing system | ||||
| DHAHRAN | c. Airintake and exhaust louvers | ||||
| Contract & BI NO. | d. Sound atteneutors | ||||
| 6600021541 / 10-00273 | e. Control system between generators, paralleling switchgearsand central controls and monitoring system. |
||||
| f. Battries and battery chargers | |||||
| g. 6-Ea, Neutrall grounding resistors | |||||
| 25 | H V A C WORKS | 18 MONTHS | LSTK INSTALLATION OF THE FOLLOWING | ||
| AT CORPORATE DATA | 2010-2012 | 1. HVAC | SAUDI ARAMCO | EYP / S.ARAMCO | |
| CENTER – S. ARAMCO | a. 6-Ea, 700 tons, centifugal, water Chillers | Latifia Cont. Co. Ltd. | Inspection Depart. | ||
| DHAHRAN | b. 40 Ea, Package AC units of 25 to 60 tons capacity | ||||
| Contract & BI NO. | c. 103-Ea, CRAH units, each of 30 tons capacity | ||||
| 6600021541 / 10-00273 | d. 72 Ea, AHUs | ||||
| e. HRUs, ARUs, EFU | |||||
| f. Duct work, Insulation & Cladding | |||||
| g. Refrigerant Piping, Insulation & Cladding | |||||
| h. Chilled water Piping and insulation | |||||
| i. Air Terminal Devices | |||||
| j. Steam Humidifier | |||||
| k. VAV’s, CAV’s, Exhuast Fan’s, Fire Smoke Dampers | |||||
| l. Testing & Commissioning and balancing. | |||||
| 26 | POWER GENERATION FOR | 6-MONTHS | LSTK INSTALLATION OF THE FOLLOWING SYSTEM | ||
| TASNEE PLASTIC RESEARCH | 2010-2011 | TASNEE | AFM CONSULTING | ||
| CENTER – JUBAIL | 1. ELECTRICAL WORKS | ||||
| CONTRACT#4500017184 | a. 4-Each 1000KW Power Generator | ||||
| b. LV Switchgear Lineup. | |||||
| c. 6000Amps ATS & Synchronizing panel. | |||||
| d. LV Cable Laying & Termination. | |||||
| e. Control Wiring B/W Generator/Synchronizing | |||||
| Panal and ATS Panel | |||||
| 2. MECHANICAL WORKS | |||||
| a. Installation of 4-EA.Diesel Generator 1000KW. | |||||
| b. 6,000 lit. Day tank. | |||||
| c. 30,000 lit. Fuel Storage Tanks. | |||||
| d. Fuel Transfer Pump System. | |||||
| e. Exhaust Mufflers. | |||||
| f. Air Inlet & Exhaust Louvers. | |||||
| g. All associated Fuel,Oil & Water sysems | |||||
| including unground & above groung piping. | |||||
| h. Commissioning of Power & Fuel System. | |||||
| 27 | HVAC ELECTRICAL | 4 MONTHS | INSTALLATION OF FOLLOWING | ||
| FIRE FIGHTING & ACCESS | 2012 | FARABI | |||
| CONTROL SYSTEM AT | 1. ELECTRICAL WORKS | ||||
| FARABI PETRO CHEMICAL | a. Step Down Transformer | ||||
| JUBAIL | b. Power Panel Board | ||||
| c. HVAC Panel | |||||
| d. Disconnect Switches | |||||
| e. Conduit & Wiring for Transformer | |||||
| f. Fire Alram System | |||||
| g. Access Control System | |||||
| 2. MECHANICAL WORKS | |||||
| a. A/C Equipment | |||||
| b. Duct Work | |||||
| c. Insulation | |||||
| e. FM 200 System Equipment | |||||
| f. FM 200 Piping & Fitting | |||||
| 28 | ELECTRICAL WORKS at SP-3 | 12 Months | EPC CONTRACT FOR THE FOLLOWING SCOPE | YASREF | YASREF/ S.ARAMCO |
| SOLID HANDLING PACKAGE | 2013-2014 | a. 480V, LV Switchgears, MCCS. | SAUDI TECHINT | Inspection Depart. | |
| YANBU, SAUDI ARABIA | b. LV Dry Type Transformers, Disconnect switches | ||||
| Contract # YOE-YERP-6600025421 (IK) | c. MV Transformers | ||||
| d. LV cable network including ter: & testing | |||||
| e. Power & Lighting Panel Boards | |||||
| f. LV ATS | |||||
| g. UPS Sysyem | |||||
| h. Grounding and lightning protection system | |||||
| i. Security and area lighting system | |||||
| 29 | HVAC WORKS at SP-3 | 12 Months | EPC CONTRACT FOR THE FOLLOWING SCOPE | YASREF | YASREF/ S.ARAMCO |
| SOLID HANDLING PACKAGE | 2013-2014 | a. AHUS | SAUDI TECHINT | Inspection Depart. | |
| YANBU, SAUDI ARABIA | b. Package AC units | ||||
| Contract # YOE-YERP-6600025421 (IK) | c. Split AC units. | ||||
| d. Ductwork including insulation. | |||||
| e. Air terminal devices. | |||||
| f. Volume, Fire dampers, control dampers, louvers etc | |||||
| 30 | MECHANICAL WORKS at SP-3 SOLID HANDLING PACKAGE CONT: # YOE-YERP-6600025421 YANBU, SAUDI ARABIS |
12 Months, 2013 – 2014 | EPC CONTRACT FOR THE FOLLOWING SCOPE | YASREF | YASREF/ S.ARAMCO |
| a. Discharge ductwork for Pastillator, manifolds and chimneys. |
SAUDI TECHINT | Inspection Depart. | |||
| 31 | CONTROL & INSTRUMENTATION WORKS at SP-7, NGL TERMINAL FACILITY, Contract # 6600028140 |
6 Months, 2013 -2014 | INSTALLATION OF THE FOLLOWING | YASREF | YASREF/ S.ARAMCO |
| a. Field junction boxes. | SAUDI ARCHIRODON | Inspection Depart. | |||
| b. Control & instrumentation cables | |||||
| c. Field instruments | |||||
| d. Cable glanding, tagging & terminations | |||||
| e. Calibration of field intruments | |||||
| f. Loop testing and commissioning. | |||||
| 32 | MEP WORKS, AT AL-ROWAD | 1-Year | INSTALLATION OF THE FOLLOWING | Al-ROWAD GLOBAL | ROWAD QC |
| B.O.P.P PLANT | 2014-2015 | SCOPE OF ELECTRICAL WORKS | |||
| DAMMAM INDUSTRIAL ESTATE 2 | a. 13.8 KV, Utility switchgears | ||||
| SUADI ARABIA | b. Paralleling Switchgear | ||||
| c. 5.6 MVA, 13.8KV Dry type power transformers | |||||
| d. 13.8KV, distribution transformers | |||||
| e. Bus ducts | |||||
| f. 380V, LV Switchgears, MCCS | |||||
| g. Plant equipment main and subdistribution panels | |||||
| h. Panel boards | |||||
| h. Plant lighting and small power | |||||
| i. MV cable network including splicing,terminations & testing | |||||
| j. LV cable network including splicing,terminations & testing | |||||
| SCOPE OF MECHANICAL WORKS | |||||
| a. 9-Ea, 2 MVA, 13.8 KV diesel engine generators | |||||
| b. Daily fuel tanks and associated piping | |||||
| c. Sound atteneutors | |||||
| d Airintake and exhaust louvers | |||||
| e. Battries and battery chargers | |||||
| f. 6-Ea, Neutrall grounding resistors | |||||
| g. Control system between generators, paralleling switchgearsand central controls and monitoring system. |
|||||
| SCOPE OF MECHANICAL WORKS | |||||
| a. Fabrication & installation of plant piping including fittings, gauges & instruments. |
|||||
| b. Fabrication & installation of piping insulation & cladding. | |||||
| d. Fabrication & installation of chilled water piping including fittings, gauges & instruments. |
|||||
| e. Fabrication & installation of CW piping insulation & cladding. | |||||
| f. Installation of Chillers, CW pumps including all instruments. | |||||
| 33 | MV CABLE NETWORK | 4 Months | INSTALLATION OF THE FOLLOWING ELECT: WORKS | SAUDI ARAMCO | S.ARAMCO |
| RCTF, RIYADH REFINERY | 2014 | a. 13.8 KV, Package substations | SAMSUNG | Inspection Depart. | |
| b. 15 KV cables including termination and testing. | |||||
| c. Grounding | |||||
