Electrical & Instrumentation Work (E&M)

NO. PROJECT & LOCATION DURATION SCOPE OF WORK OWNER / CLIENT INSPECTION /
SUPERVISION
1 ELECTRICAL & 6-MONTHS LSTK INSTALLATION OF THE FOLLOWING SAUDI ARAMCO
  INSTRUMENTATION 2005-2006 ELECTRICAL, INSTRUMENTATION AND SCADA Saudi Aramco INSPECTIONS
  AND SCADA SYSTEMS FOR RTUS ON WELL HEADS DEPARTMENT
  FOR HARADH GOSP-3   1. ELECTRICAL
  STARTUP WELLS a. Main Power supply
  HARADH, SAUDI ARABIA b. L.V Transformers
c. Power Panel Boards
d. Starters, Pushbutton stations.
e. Disconnect switches
f. Switch Racks, Cable trays, conduits and fittings
g. LV cables
  2. INSTRUMENTATION WORKS
a. DCS Marshalling Cabinets
b. SCADA control cabinets
c. Digital & Analog process instruments
d. Digital & Analog Field Junction Boxes.
e. Calibration of field instruments
f. Switch Racks, Cable trays, RGS/PVC coated
   conduits and fittings
g. Control, instrumentation & comm: cables
h. Termination & loop checks
i.  Precommissioning & startup.
2 ELECTRICAL & 6-MONTHS LSTK INSTALLATION OF THE FOLLOWING SAUDI ARAMCO
  COMMUNICATION WORKS 2005-2006 ELECTRICAL, ELECTRICAL AND COMM: Saudi Aramco INSPECTIONS
  FOR SCADA SYSTEM SYSTEMS DEPARTMENT
  AT UTHMANIYAH   1. ELECTRICAL
  GAS PLANT a. Main Power supply
  UTHMANIYAH, SAUDI ARABIA b. L.V Transformers
c. Power Panel Boards
d. Disconnect switches
e. RGS conduits and fittings
f. LV cables
  2. COMMUNICATION WORKS
a. DCS Marshalling Cabinets
b. SCADA control consoles
c. Cable trays, RGS conduits and fittings
d. Data cables
e. Data outlets
f. Termination & loop checks
g. Precommissioning & startup.
3 ELECTRICAL & 8-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  INSTRUMENTATION 2006-2007 ELECTRICAL & INSTRUMENTATION WORKS Saudi German Saudi Engineering
 AT SAUDI GERMAN PLANT   1. ELECTRICAL Industries-Dammam Dammam
FOR NON WOVEN FIBRE a. MV Package substations
DAMMAM INDUSTRIAL b. Ring Main Units
AREA-II c. Distribution Transformers
d. LV switchgears
e. Power Bus Ducts
f. Motor control centres
g. Panel Boards, starters, Pushbutton stations.
h. Disconnect switches
i.  Lighting system
k. Pipe Racks, Cable trays, conduits and fittings
l.  HV/LV cables
      m Control cables    
2. INSTRUMENTATION WORKS
a. DCS Marshalling Cabinets
b. DCS control consoles
c. Digital & Analog process instruments
d. Digital & Analog Field Junction Boxes.
e. Calibration of field instruments
f. Pipe Racks, Cable trays, conduits and fittings
g. Control, digital & analog cables
h. Termination & loop checks
h. Precommissioning & Plant startup.
4 ELECTRICAL & 12-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  INSTRUMENTATION 2006-2007 ELECTRICAL & INSTRUMENTATION WORKS JANA HASSAD
   AT JANA PLANT 1. ELECTRICAL
  JUBAIL INDUSTRIAL a. MV switchgear Lineup
  AREA b. Power Transformers
c. Distribution Transformers
d. Rectifier transformers
e. Power Bus Ducts
f. LV switchgears
g. Motor control centres
h. Power factor correction equipment
i. Panel Boards, starters, Pushbutton stations.
k.Disconnect switches
l. Pipe Racks, Cable trays, conduits and fittings
m HV/LV cables
n. Control cables
0.  Plant Lighting & Power Distribution network
  2. INSTRUMENTATION WORKS
a. DCS Marshalling Cabinets
b. DCS control consoles
c. Digital & Analog process instruments
d. Digital & Analog Field Junction Boxes.
e. Calibration of field instruments
f. Pipe Racks, Cable trays, conduits and fittings
g. Control, digital & analog cables
h. Termination & loop checks
h. Precommissioning & Plant startup.
  3. COMMUNICATION WORKS
a. Cable trays, RGS conduits and fittings
b. SCADA control consoles
c. Data cables
d. Data outlets
e. Termination & loop checks
f. Precommissioning & startup.
5 ELECTRICAL WORKS 08-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  AT BISCHOF + KLIEN 2006-2007 ELECTRICAL & INSTRUMENTATION WORKS BISHOF + KLIEN B+K
  MIDDLE EAST CO.   1. ELECTRICAL MIDDLE EAST CO.
  DAMMAM INDUSTRIAL a. Ring Main Units
  AREA – II b. Distribution Transformers
c. LV switchgears
d. Power Bus Ducts
e. Motor control centres
f. Panel Boards, starters, Pushbutton stations.
g. Disconnect switches
h. Lighting system
i. Cable trays, conduits and fittings
j. HV/LV cables
k Control cables
l. Fire Alarm System
6 TIMELINE SADAF 1.5-MONTH DCS CONTROL, HMI & ELECTROMECHANICAL SADAF ABB
  EDC T/A 2007 Jan-Feb 2007 WORKS DURING SHUTDOWN PERIOD SWITZERLAND
  SAUDI PETROCHEMICAL   1. CONTROL ROOM
  CO. (SADAF) JUBAIL a. Removal of existing HMI.
b. Installation of New HMI
c. Disconnect & removal of existing control cables
d. Installation of New Control cables from
    Marshalling rack to New HMI
f. Modification of existing DCs Panel to increase
   Capacity
  2. RECTIFIER TRANSFORMERS – 6 EA
a Dismental & remove existing power & control
   wiring for rectifier transformers including control
   panel.
b. Installation of New control panel for rectifier
    transformers.
c. Modification work at Pan alarm panel
d. Installation of cotnrol & communication wiring
    from rectifier transformer and marshalling racks.
e. Preloop checks & final loop checks.
f. Replacement of RTD’s at rectifier transformer
g. Replacemnt of existing switches & transmitter.
   
  3. MECHANICAL WORKS
a. Cleaning of rectifier transformer bushing with
   Demi water.
b. Replacement of gaskits.
c. Replacement of mehcanical piping at various
    Locations.
d. Re-circulation & Dehumidification of
    transformer oil.
7 FOUNDATION HEATING 4-MONTHS LSTK INSTALLATION OF THE FOLLOWING ELECTRICAL SHARQ/SABIC FOSTER WHEELER
  SYSTEM FOR TANKS 2007-2008 AND HEATING SYSTEM WORK. FOSTER WHEELER ACBI LTD
  AT SHARQ-III EXPENSION   1. ELECTRICAL
  PROJ.# 1-14-2460/2519 a. Marshaling Panel for Heating system
  JUBAIL IND. CITY b. Marshaling Panel for Cool down system
c. Control Panel for Heating / Cool Down system
d. Power JB’s for Heating elements/RTD’s
e. Power / Heating Cable
f. RTD’s for Heating / Cool Down system
g. Cable trys, Conduit & Fitting
h. Grounding system
8 HVAC / FIRE FIGHTING 06-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  WORKS AT IBN-ZAHR 2007-2008 HVAC & FIRE FIGHTING SYSTEM IBN-ZAHR DAELIM/KCC
  EXPENSION PROJECT   1. HVAC DAELIM S.A. JUBAIL
  JUBAIL INDUSTRIAL CITY a. 50-Ton Package A/C units
b. 5-Ton Split A/C units
c. Power and Control Cables
d. Control Panel
e. Duct Work, Insulation & Cladding
f. Refrigerant Piping, Instulation & Cladding
g. Cable Tray Conduit & Fittings
h. Testing & Commissioning
  2. FIRE FIGHTING
a. Above Ground Fire Water Piping System
b. FM-200 System
c. Fire Hydrant & Assocciate Equipment
d. Tesing & Commissioning
9 CASE WORK & GAS 3-MONTHS LSTK INSTALLATION OF THE FOLLOWING SYSTEM IBN-ZAHR DAELIM/KCC
  TUBING NET WORK AT 2008 DAELIM S.A. JUBAIL
  LAB BUILDING IBN-ZAHR   1. GAS PIPING + BUNKER
  JUBAIL IND. CITY a. Installation of SS-Tubing network for the
    following gases & Utilities:
    * HE ( HELIUM )
    * N2 ( NITROGEN )
    * O2 ( OXYGEN )
    * ARGON
    * IA ( INST. AIR )
    * PW ( PORTABLE WATER )
    * NO ( NITREX OXIDE )
    * 3-Stage Manifolds
    * Air Seperator Filter System
    * Testing & Commissioning
    2. CASE WORK
a. Installation of LAB Accessories for the following
    * Fume Hood
    * Work Benches
    * Plumbing for Case Work
    * Electrical for Case work
    * Power Out let
    * Data Out let
    * Wiring & Termination
10 CASE WORK & GAS 4-MONTHS LSTK INSTALLATION OF THE FOLLOWING SYSTEM SIPCHEM FLOUR S.A
  UTILITIES NETWORK AT 2008 1. GAS PIPING + BUNKER JUBAIL
  SAUDI INTERNATIONAL a. Installation of SS-Tubing network for the
  PETRO CHEMICAL CO.     following gases & Utilities:
  SIPCHEM – JUBAIL     * HE ( HELIUM )
  CONTRACT#JAC-C-173-B     * N2 ( NITROGEN )
    * O2 ( OXYGEN )
    * ARGON
    * IA ( INST. AIR )
    * PW ( PORTABLE WATER )
    * NO ( NITREX OXIDE )
    * 3-Stage Manifolds
    * Air Seperator Filter System
    * Testing & Commissioning
  2. CASE WORK
a. Installation of LAB Accessories for the following
    * Fume Hood
    * Work Benches
    * Plumbing for Case Work
    * Electrical for Case work
    * Power Out let
    * Data Out let
    * Wiring & Termination
11 ELECTRICAL & 06-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  INSTRUMENTATION AT 2008 ELECTRICAL & INSTRUMENTATION WORKS SAUDI ARAMCO AL-KHODARI
  TURAIF BULK PLANT-X20   1. ELECTRICAL & SONS CO.
  SAUDI ARAMCO a. Power Bus Ducts SAPMT
  JO/EWO# 10-00084/0001 b. LV switchgears
  SA-CONT#6600018226 c. Motor control centres
  SA-CONT#6600018227 d. Panel Boards, starters, Pushbutton stations.
e.Disconnect switches
f. Cable trays, conduits and fittings
g LV cables
h. Control cables
i.  Plant Lighting & Power Distribution network
  2. INSTRUMENTATION WORKS
a. Digital & Analog process instruments
b. Digital & Analog Field Junction Boxes.
c. Calibration of field instruments
d.  Cable trays, conduits and fittings
e. Control, digital & analog cables
f. Termination & loop checks
g. Precommissioning & Plant startup.
12 ELECTRICAL & 06-MONTHS LSTK INSTALLATION OF THE FOLLOWING SAUDI ARAMCO AL-KHODARI
  INSTRUMENTATION AT 2008 ELECTRICAL & INSTRUMENTATION WORKS & SONS CO.
  JOUF BULK PLANT-X19   1. ELECTRICAL SAPMT
  SAUDI ARAMCO a. Power Bus Ducts
  JO/EWO# 10-00084/0001 b. LV switchgears
  SA-CONT#6600018226 c. Motor control centres
  SA-CONT#6600018227 d. Panel Boards, starters, Pushbutton stations.
e.Disconnect switches
f. Cable trays, conduits and fittings
g LV cables
h. Control cables
i.  Plant Lighting & Power Distribution network
  2. INSTRUMENTATION WORKS
a. Digital & Analog process instruments
b. Digital & Analog Field Junction Boxes.
c. Calibration of field instruments
d.  Cable trays, conduits and fittings
e. Control, digital & analog cables
f. Termination & loop checks
g. Precommissioning & Plant startup.
13 HVAC / FIRE FIGHTING 04-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  WORKS AT LAB BUILDING 2008 HVAC & FIRE FIGHTING SYSTEM AR-RAZI MHI / KCC
  AR-RAZI METHONAL   1. HVAC MHI JUBAIL
  PROJECT PLANT-V a. 50-Ton Package A/C units
  JUBAIL INDUSTRIAL CITY b. 5-Ton Split A/C units
  Contract# 533570 c. Power and Control Cables
d. Control Panel
e. Duct Work, Insulation & Cladding
f. Refrigerant Piping, Instulation & Cladding
g. Cable Tray Conduit & Fittings
h. Testing & Commissioning
  2. FIRE FIGHTING
a. Above Ground Fire Water Piping System
b. FM-200 System
c. Fire Hydrant & Assocciate Equipment
d. Tesing & Commissioning
14 HVAC WORKS AT 3-MONTHS LSTK INSTALLATION OF THE FOLLOWING SASREF SASREF /
  AT SASREF JUBAIL 2008 HVAC SYSTEM CARRIER
a- 50 Ton Package A/C Units
b. Power and Control Cables
c. Control Panel
d. Duct Work, Insulation & Cladding
e. Refrigerant Piping, Instulation & Cladding
f. Cable Tray Conduit & Fittings
g. Testing & Commissioning
   
15 ONLINE ANALYZER FOR 2-MONTHS LSTK INSTALLATION OF THE FOLLOWING SASREF SASREF /
  OIL & BENZENE 2008 ABDULALH FOUAD
  AT SASREF JUBAIL a- Analyzer
b- Cable Tray Conduit & Fittings
c- Sampling Tube Laying & termination.
d. Power and Control Cables
e- Hookup with DCS in Control Room.
16 ELECTRICAL & 8-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  INSTRUMENTATION 2009 ELECTRICAL & INSTRUMENTATION WORKS PROCTER & GAMBLE MIC /
  AT CORNFLAKE PLANT   1. ELECTRICAL CHEMOPRAG,
  2ND INDUSTRIAL CITY a. MV switchgear Lineup CHEZK REPUBLIC
  DAMMAM b. Power Transformers
c. Distribution Transformers
d. Rectifier transformers
e. Power Bus Ducts
f. LV switchgears
g. Motor control centres
h. Power factor correction equipment
i. Panel Boards, starters, Pushbutton stations.
k.Disconnect switches
l. Pipe Racks, Cable trays, conduits and fittings
m HV/LV cables
n. Control cables
0.  Plant Lighting & Power Distribution network
  2. INSTRUMENTATION WORKS
a. DCS Marshalling Cabinets
b. DCS control consoles
c. Digital & Analog process instruments
d. Digital & Analog Field Junction Boxes.
e. Calibration of field instruments
f. Pipe Racks, Cable trays, conduits and fittings
g. Control, digital & analog cables
h. Termination & loop checks
h. Precommissioning & Plant startup.
17 HVAC / FIRE FIGHTING / 1-YEAR LSTK INSTALLATION OF THE FOLLOWING
  ELECTRICAL / BMS WORKS 2009-2010 HVAC & FIRE FIGHTING SYSTEM AAC ETHYLENE AAC /
  AT AAC ETHYLENE AMINES   1. HVAC AMINE HANWHA SAUDI
  PLANT a. Chiller CONTRACTING CO.
  JUBAIL INDUSTRIAL CITY b. Package units LTD.
  Contract# HSCC-AAC-027 c. Splilt units
d. AHUs
e. HRUs, ARUs, EFU
f. Power & Control Cables
g. Control Panel
h. Duct work, Insulation & Cladding
i.  Refrigerant Piping, Insulation & Cladding
j.  Cable Tray, Conduit & Fittings
k. Testing & Commissioning
  2. FIRE FIGHTING
a. Above Ground Fire Water Piping System
b. FM-200 System
c. Fire Hydrant & Associate Equipment
d. Testing & Commissioning
  3. PLUMBING
a. Hot & Cold water system
b. Drain & Sewer water system
c. Chemical Drainage system
d. Plumbing Fixtures & Fittings
e. Eye wash & Safety Shower
f. Copper piping Networks
18 ELECTRICAL WORKS FOR 4-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  NEW PSG BUILDING 2009-2010 ELECTRICAL & DATA NETWORKING PROCTER & GAMBLE MIC
  AT PROCTOR & GAMBLE   1. ELECTRICAL
  MODERN INDUS. CO. a. LV switchgear Lineup
  DAMMAM b. Distribution Transformers
c. Motor control centres
d. Panel Boards, starters, Pushbutton stations.
e. Disconnect switches
f. Pipe Racks, Cable trays, conduits and fittings
g. LV cables
h. Control cables
i.  Plant Lighting & Power Distribution network
  2. TELEPHONE & DATA NETWORKS
a. Data Panels
b. Telephone & Data Outlets
C. Patch Cords & Patch Panels
d. Cable trays, conduits and fittings
e. Termination & loop checks
f. Precommissioning & startup.
   
19 MEDUIM VOLTAGE 3-MONTHS LSTK INSTALLATION OF THE FOLLOWING
  POWER DISTRIBUTION 2010 ELECTRICAL WORKS PROCTER & GAMBLE MIC
  NETWORKS @   1. ELECTRICAL
  P&G / MIC a. MV Package substations
  DAMMAM INDUSTRIAL b. Ring Main Units
  AREA-II c. Distribution Transformers
d. LV switchgears
e. Power Bus Ducts
f. Motor control centres
g. MV REYCHEM Termination & Hi-pot
h. Pipe Racks, Cable trays, conduits and fittings
l.  HV/LV cables
20 CASE WORK & GAS 8-MONTHS LSTK INSTALLATION OF THE FOLLOWING SYSTEM
  UTILITIES NETWORK AT 2010 1. GAS PIPING + BUNKER TASNEE AFM CONSULTING
  TASNEE PLASTIC RESEARCH a. Installation of SS-Tubing network for the H&H SCIENTIFIC
  CENTER – JUBAIL     following gases & Utilities: CANADA
  CONTRACT#4500014754     * HE ( HELIUM )
    * N2 ( NITROGEN )
    * O2 ( OXYGEN )
    * ARGON
    * IA ( INST. AIR )
    * PW ( PORTABLE WATER )
    * NO ( NITREX OXIDE )
    * 3-Stage Manifolds
    * Air Seperator Filter System
    * Testing & Commissioning
  2. CASE WORK
a. Installation of LAB Accessories for the following
    * Fume Hood
    * Work Benches
    * Plumbing for Case Work
    * Electrical for Case work
    * Power Out let
    * Data Out let
    * Wiring & Termination
21 ELECTRO MECHANICAL 9-MONTHS LSTK INSTALLATION OF THE FOLLOWING SYSTEM
  WORKS AT 2010 TASNEE AFM CONSULTING
  TASNEE PLASTIC RESEARCH   1. PROCESS COOLING SYSTEM
  CENTER – JUBAIL a. 200 Ton Chiller
  CONTRACT#4500016585 b. Heat Exchanger, ch.water pump, pw pumps
c. 6″ chiller water line for all process machines
d. 3″ chilled water riser to the headers,
e. Complete system upto the commissioning.
  2. COMPRESSED AIR SYSTEM
a. 2″ air line to all process machines
b. Compressor and filtration system including
    tank
c. Commissioning of complete system
  3. MACHINE ERECTION
a. Below film line
b. Small injector
c. Large below film line
d. Large injector machine
E. Pipe extruder
F. Chiller units
g. Testing & Commissioning of all Machine’s
22 INSTALLATION OF MV/LV 1-Year INSTALLATION OF THE FOLLOWING
  CABLE NETWORK 2010-2011 MV/LV CABLES INCLUDING TEMINATION & TESTING SAUDI ARAMCO EYP / S.ARAMCO
  INCLUDING TERMINATION Latifia Cont. Co. Ltd. Inspection Depart.
  AND TESTING AT SAUDI a. 15-KV, Underground cables in duct bank
  ARAMCO CORPORATE b. 7.2-Kv Cables in duct bank
  DATA CENTER – DHAHRAN c.  LV Cable in duct bank, cable tray & Conduits
  Contract & BI NO. d. 15-KV, splicing & terminations
  6600021541 / 10-00273 e. Dressing, termination, tagging of MV cables
f.  Meggering & Hi-pot
g.  Dressing, termination, tagging of LV cables
h.  Insulation resistance testing of a power & control
cables
23 INSTALLATION OF MV/LV 1-Year INSTALLATION OF THE FOLLOWING
  POWER SYSTEM EQUIPMENTS 2011-2012 ELECTRICAL EQUIPMENTS SAUDI ARAMCO EYP / S.ARAMCO
  AT SAUDI ARAMCO a. 13.8 KV, double ended Utility switchgears Latifia Cont. Co. Ltd. Inspection Depart.
  CORPORATE DATA CENTER b. 13.8 KV double ended Paralleling Switchgear
  DHAHRAN c.  5 KV double ended Switchgear
  Contract & BI NO. d. 13.8KV, Automatic Transfer Switches
  6600021541 / 10-00273 e. 13.8 KV Manual Transfer Switches
f.  3.75MVA, Power transformers
g. 7.5 MVA power transpformers
h. LV Dry Type Transformers
i. 480V, double ended LV Switchgears
j. 750 KVA UPS
k. 40 KVA UPS
l. 85 KVA UPS
m. Static Transfer Switches
n. Motor Control Centers
o. Power distribution units (PDUS)
p. RPP
q. LV, Distribution Panel Boards
r. LV Automatic tranfer switches
s. DC, Disconnect Switchs
t. Batteries, battry banks & Battery Chargers
24 INSTALLATION OF MV/LV 1-Year INSTALLATION OF THE FOLLOWING
  EMERGENCY POWER SYSTEM 2011-2012 a.  6-Ea, 2 MVA, 13.8 KV, Diesel engine generators SAUDI ARAMCO EYP / S.ARAMCO
  AT SAUDI ARAMCO a.  6-Ea, Diesel fuel tanks Latifia Cont. Co. Ltd. Inspection Depart.
  CORPORATE DATA CENTER b.  Fuel polishing system
  DHAHRAN c.  Airintake and exhaust louvers
  Contract & BI NO. d.  Sound atteneutors
  6600021541 / 10-00273 e.  Control system between generators, paralleling
switchgearsand central controls and monitoring system.
f.  Battries and battery chargers
g. 6-Ea, Neutrall grounding resistors
25 H V A C WORKS 18 MONTHS LSTK INSTALLATION OF THE FOLLOWING
  AT CORPORATE DATA 2010-2012 1. HVAC SAUDI ARAMCO EYP / S.ARAMCO
  CENTER – S. ARAMCO a. 6-Ea, 700 tons, centifugal, water Chillers Latifia Cont. Co. Ltd. Inspection Depart.
  DHAHRAN b. 40 Ea, Package AC units of 25 to 60 tons capacity
  Contract & BI NO. c. 103-Ea, CRAH units, each of 30 tons capacity
  6600021541 / 10-00273 d. 72 Ea, AHUs
e. HRUs, ARUs, EFU
f. Duct work, Insulation & Cladding
g. Refrigerant Piping, Insulation & Cladding
h. Chilled water Piping and insulation
i. Air Terminal Devices
j. Steam Humidifier
k. VAV’s, CAV’s, Exhuast Fan’s, Fire Smoke Dampers
l. Testing & Commissioning and balancing.
26 POWER GENERATION FOR 6-MONTHS LSTK INSTALLATION OF THE FOLLOWING SYSTEM
  TASNEE PLASTIC RESEARCH 2010-2011 TASNEE AFM CONSULTING
  CENTER – JUBAIL   1. ELECTRICAL WORKS
  CONTRACT#4500017184 a. 4-Each 1000KW Power Generator
b. LV Switchgear Lineup.
c. 6000Amps ATS & Synchronizing panel.
d. LV Cable Laying & Termination.
e. Control Wiring B/W Generator/Synchronizing
    Panal and ATS Panel
  2. MECHANICAL WORKS
a. Installation of 4-EA.Diesel Generator 1000KW.
b. 6,000 lit. Day tank.
c. 30,000 lit. Fuel Storage Tanks.
d. Fuel Transfer Pump System.
e. Exhaust Mufflers.
f. Air Inlet & Exhaust Louvers.
g. All associated Fuel,Oil & Water sysems
    including unground & above groung piping.
h. Commissioning of Power & Fuel System.
27 HVAC ELECTRICAL 4 MONTHS INSTALLATION OF FOLLOWING
  FIRE FIGHTING & ACCESS 2012 FARABI
  CONTROL SYSTEM AT   1. ELECTRICAL WORKS
  FARABI PETRO CHEMICAL a. Step Down Transformer
  JUBAIL b. Power Panel Board
c. HVAC Panel
d. Disconnect Switches
e. Conduit & Wiring for Transformer
f. Fire Alram System
g. Access Control System
  2. MECHANICAL WORKS
a. A/C Equipment
b. Duct Work
c. Insulation
e. FM 200 System Equipment
f. FM 200 Piping & Fitting
28 ELECTRICAL WORKS at SP-3 12 Months EPC CONTRACT FOR THE FOLLOWING SCOPE YASREF YASREF/ S.ARAMCO
  SOLID HANDLING PACKAGE 2013-2014 a. 480V, LV Switchgears, MCCS. SAUDI TECHINT Inspection Depart.
  YANBU, SAUDI ARABIA b. LV Dry Type Transformers, Disconnect switches
  Contract # YOE-YERP-6600025421 (IK) c. MV Transformers
d. LV cable network including ter: & testing
e. Power & Lighting Panel Boards
f. LV ATS
g. UPS Sysyem
h. Grounding and lightning protection system
i.  Security and area lighting system
29 HVAC WORKS at SP-3 12 Months EPC CONTRACT FOR THE FOLLOWING SCOPE YASREF YASREF/ S.ARAMCO
  SOLID HANDLING PACKAGE 2013-2014 a. AHUS SAUDI TECHINT Inspection Depart.
  YANBU, SAUDI ARABIA b. Package AC units
  Contract # YOE-YERP-6600025421 (IK) c. Split AC units.
d. Ductwork including insulation.
e. Air terminal devices.
f. Volume, Fire dampers, control dampers, louvers etc
30 MECHANICAL WORKS at SP-3
SOLID HANDLING PACKAGE
CONT: # YOE-YERP-6600025421
YANBU, SAUDI ARABIS
12 Months, 2013 – 2014 EPC CONTRACT FOR THE FOLLOWING SCOPE YASREF YASREF/ S.ARAMCO
  a. Discharge ductwork for Pastillator, manifolds and
chimneys.
SAUDI TECHINT Inspection Depart.
31 CONTROL & INSTRUMENTATION WORKS at SP-7, NGL TERMINAL
FACILITY, Contract # 6600028140
6 Months, 2013 -2014 INSTALLATION OF THE FOLLOWING YASREF YASREF/ S.ARAMCO
  a. Field junction boxes. SAUDI ARCHIRODON Inspection Depart.
  b. Control & instrumentation cables
  c. Field instruments
  d. Cable glanding, tagging & terminations
  e. Calibration of field intruments
  f. Loop testing and commissioning.
32 MEP WORKS, AT AL-ROWAD 1-Year INSTALLATION OF THE FOLLOWING Al-ROWAD GLOBAL ROWAD QC
  B.O.P.P PLANT 2014-2015 SCOPE OF ELECTRICAL WORKS
  DAMMAM INDUSTRIAL ESTATE 2 a. 13.8 KV, Utility switchgears
  SUADI ARABIA b.  Paralleling Switchgear
c.  5.6 MVA, 13.8KV Dry type power transformers
d. 13.8KV, distribution transformers
e.  Bus ducts
f.  380V, LV Switchgears, MCCS
g.  Plant equipment main and subdistribution panels
h.  Panel boards
h.  Plant lighting and small power
i.   MV cable network including splicing,terminations & testing
j.   LV cable network including splicing,terminations & testing
SCOPE OF MECHANICAL WORKS
a. 9-Ea, 2 MVA, 13.8 KV diesel engine generators
b. Daily fuel tanks and associated piping
c. Sound atteneutors
d  Airintake and exhaust louvers
e.  Battries and battery chargers
f. 6-Ea, Neutrall grounding resistors
g.  Control system between generators, paralleling
switchgearsand central controls and monitoring system.
SCOPE OF MECHANICAL WORKS
a. Fabrication & installation of plant piping including
fittings, gauges & instruments.
b. Fabrication & installation of piping insulation & cladding.
d. Fabrication & installation of chilled water piping including
fittings, gauges & instruments.
e. Fabrication & installation of CW piping insulation & cladding.
f.  Installation of Chillers, CW pumps including all instruments.
33 MV CABLE NETWORK 4 Months INSTALLATION OF THE FOLLOWING ELECT: WORKS SAUDI ARAMCO S.ARAMCO
  RCTF, RIYADH REFINERY 2014 a. 13.8 KV, Package substations SAMSUNG Inspection Depart.
b. 15 KV cables including termination and testing.
c. Grounding